Huaiyin Avenue under Rapid Transformation

图片7.png


Recently, constructors were backfilling the earthwork for the embedded pipeline in the section from the Hangkong Intersection of Huaiyin Avenue to Taizi Street in Xiaogan City. The comprehensive reconstruction project of Huaiyin Avenue has a total length of 7.18km. So far, 75% of tap water, sewage, rainwater pipeline embedment and earthwork backfilling along the south side of the road have been completed, and it is expected to be completed by the end of December. All construction tasks, including strong and weak power pipeline arrangement, water-stable base course of pavement and asphalt concrete paving of pavement, can be completed by the end of January 2021, and then, the north side will be constructed.